References

Examples of Allplan Engineering and impressive projects around the world.

Greater efficiency thanks to 3D Planning

Four-track extension between Olten and Aarau (Eppenberg Tunnel), Switzerland

By the end of 2021, the four-track extension of the Olten-Aarau route is expected to relieve one of the most severe bottlenecks on the east-west axis of the Swiss rail network. The project, costing CHF 855 million, includes expansions in the east of Olten, a fourth 2.5-kilometer-long track between Dulliken and Däniken and – as the core element – the double-track, three-kilometer-long Eppenberg Tunnel and comprehensive measures for its connection.

The challenge:

How are several thousand anchors in a geometrically complex excavation pit at a very narrow offset between axles and with holes at many different angles planned in an efficient manner, and how is it ensured that no collisions occur under the holes? And how is it ensured that existing vertical holes are not destroyed by the pipes for the inclinometer measurements with the anchor and relief holes to be drilled?

The solution:

“If we had planned this complex excavation pit in 2D, it would have been necessary to develop a multitude of cutting plans,” says Rainer Hohermuth, before going on to point out: “Even so, we would never have been sure whether ...


Read the full story




Case Study Package Engineering -
Get more than 15 interesting Case Studies in one package

See from the customer's point of view how Allplan Engineering was used in different challenging customer projects and contributed tremendously to their success.

Discover new challenges and complex problems in customer projects solved with modern CAD Software. See for yourself how solutions from ALLPLAN enabled the realisation of different exclusive projects.

Your advantages at a glance:

  • More than 15 exclusive projects with challenges and suitable approaches to the right solution
  • All project challenges and their approach from the customer's point of view
  • Case Studies in pdf format
  • Exclusive insights into customer projects using CAD Software

check out the Case Study Package Engineering


Challenging Access

Access Structures, The Circle, Zurich Airport, Switzerland

With a total investment cost of around CHF 1 billion, at the foot of the Butzenbüel hill and within walking distance of the terminal, a high-quality superstructure for services is emerging that will provide a usable area of 180,000 square meters. The first and second stages are expected to be completed at the end of 2018 and in 2019 respectively.

The challenge:

Centering for the construction of the central ramp bridge was a major challenge during spatial positioning. According to the current state of planning, this ramp bridge is located in close proximity to a planned protection platform over the Butzenbüelring, which will be necessary to construct the building’s partly overhanging facade. The central ramp bridge also crosses over one point of the current exit from the airport drop-off area at a very oblique angle.

The solution:

The smooth import of 3D data for the existing structures and the planned building complex meant that he had an ideal starting point to integrate the new access structures into these layouts. Although both this data and the digital terrain model were partially developed using software from other providers, the data was exchanged without any problems. Development in the 3D model was particularly ...


Read the full story

The Groundbreaking Tunnel

Gotthard Base Tunnel, Switzerland

The scheduled commissioning on December 11, 2016, marked the end of the project of the century – the Gotthard Base Tunnel – after nearly 20 years of building time. Its route length of 57 kilometers through the Saint-Gotthard Massif between Erstfeld and Bodio makes the Gotthard Base Tunnel the longest rail tunnel in the world.

The challenge:

The entire base tunnel, including cross-passages and multifunction stations, is double-walled. After the excavation support, a seal and an insituconcrete tunnel lining were installed. In the Erstfeld and Amsteg sections, the contractor used three formwork units, each with two 10-meterlong formwork carriages, for the cladding and tunnel lining. In an ultimate feat of logistics, up to 60 meters of cladding was concreted per day. That is to say, for every ten months of building time, over 22 kilometers of tunnel lining were laid per tube.

The solution:

The engineers from Gähler und Partner used planning in 3D anywhere there were difficult sections or problem areas to be able to best edit these components with the help of visualizations. ...


Read the full story

Three centuries of bridge building over the Firth of Forth

Reinforced concrete pylon with cablestayed tensioning and suspended roadway during the construction phase.

The Queensferry Crossing near Edinburgh in Scotland is a cablestayed bridge with three pylons over 200 m in height. It is one of the largest infrastructure projects in Europe and benefitted from ultramodern reinforcement planning in 3D thanks to the engineers from Leonhardt, Andrä und Partner (LAP) and Allplan Engineering.

The challenge:

Transport Scotland’s consultants from the Jacobs Arup joint venture were not given an easy task in developing a concept for the new bridge. The bridge has to be an equal counterpart to the world cultural heritage of the "Forth Bridge."

The solution:

The reinforcement of the individual pylon segments had to be placed precisely in the space due to the upwardtapering crosssection. This method placed high demands on the CAD software used. That is why planners from LAP also relied on Allplan Engineering for the reinforcement and ...


Read the full story

Function and design – XXL

Sava Bridge, Belgrade / Serbia

Belgrade lies at the confluence of the Danube and Sava rivers. For years, expansion of the northern suburbs of the city has been hindered by the limited capacity of the three existing bridges over the Sava: the Brankov most, Savski most, and Gazela. In order to expand the capacity of the transport network, a fourth bridge is currently being built over the Sava.

The challenge:

The project is a complex one, and not only because of the dimensions involved. In order to ensure uninterrupted shipping movements during the construction period, the main section spanning the Sava must be erected in the river without temporary supports. In addition, construction will be going ahead on different sections simultaneously. The side section, for example, will be erected parallel to the main bridge, yet independently of it.

The solution:

Depending on the specific need, the engineers have combined 2D and 3D planning, a classic example of hybrid working. “For the typical standard tasks in the planning of bridges, 2D planning is entirely sufficient, but more complex points are nowadays being planned increasingly in 3D,” states Steffen Kühn, structural designer at Leonhardt, Andrä and Partner. Formwork and tendon stress planning, for example, have been carried out in 2D, while 3D planning ...


Read the full story

Bridging the gap for more than a century

Versamertobel Bridge, Graubünden Canton, Switzerland

As an example of steel bridge building at the turn of the century, the structure is of considerable historic value, but it is no longer up to the demands of current times. The bridge has been deemed worthy of preservation and therefore has escaped being torn down and instead continues to serve the traveler as an additional link for slower traffic.

The challenge:

The brief had to consider the dramatic surroundings, the slender lines of the adjacent existing steel bridge, the difficulties of construction and the requirements for durability.

The solution:

All the drawings were prepared using the BIM solution Allplan, which confirmed in particular on this project its credentials as an easy-to-use, intuitive 3D design tool. This was apparent in considering the steep ground around the foundation excavations, at the connection of the ...


Read the full story

Flowing crossover

Campus Bridge Würzburg, Germany

There is more behind the “campus bridge” than the pure avoidance of stopping traffic. The new university campus Hubland North is located on a former US military base: the Leighton area. After the US forces left this in 2009, the state of Bavaria purchased part of the land for the University of Würzburg and had parts of the former military facility converted for university use.

The challenge:

The team of Dr. Schütz Ingenieure (Kempten), Kolb Ripke Architekten and POLA Landschaftsarchitekten (both Berlin) created a design that was implemented in a single-stage realization competition at the turn of the year 2011/2012: a sophisticated structure, consisting of two narrow concrete strips converging into a small square above the street.

The solution:

Dr. Schütz Ingenieure used Allplan Engineering to model the iconic structure. With Allplan Engineering software, it was possible to optimally illustrate the complexity of the bridge in the 3D modeling. In the process, the 3D modeling of reinforcement drawings in particular contributed to ...


Read the full story

Skyscraper with unconventional building geometry

Limmat Tower Dietikon, Switzerland

With the 80 meter high Limmat Tower, the Limmat Valley in Switzerland has its first skyscraper, which could become the landmark of the town of Dietikon, or the whole region. "The Limmat Tower stands for innovation, uniqueness and prospect," said Maik Neuhaus, head of development at Halter AG, at the turf-cutting ceremony in June 2013.

The challenge:

Direct force transmission was impossible in various places due to the façade folding and the projections and recesses. The support forces also needed to be absorbed or diverted at the building recesses. And, in terms of fire protection, in high-rise buildings the fire must be prevented from spreading by the circumferential parapet.

The solution:

Thanks to the model-based development of the formwork and reinforcement plans with the Allplan Engineering software and the possibility of 3D visualisation, the engineering firm Synaxis was able to optimally deal with the sophisticated details in particular in a way that suited the construction site. ...

Read the full story

Software-assisted planning competence assures high quality standard

When compared internationally, engineering offices are expected to cope with high demands. This can only be achieved by maintaining permanent willingness to innovate and it demands continuous examination of the latest technical trends. MUCKINGENIEURE has an excellent track record when it comes to planning complex building structures using Allplan Engineering.

The challenge:

The common aim is to produce a construction plan that is an economic success.

The solution:

MUCKINGENIEURE works using a 3D BIM model and stored attributes to increase flexibility in the face of requested changes and as a reliable method of verifying their feasibility. The engineers normally draw up lists and attributes themselves, since Allplan Engineering offers the opportunity to program individual reports, or save components and their properties. ...

Read the full story

Shining debut for a new city quartier

Office building Aviatica, Prague, Czech Republic

The former factory premises of aircraft engine manufacturer Waltrovka / Walter Engines is located in the district of Jinonice, in the fifth administrative department of Prague. Investment management group Penta Investments is planning to build a new city quarter with three office complexes (Aviatica, Dynamica and Mechanica) and various residential complexes on this 169,000 m² site in the coming years.

The challenge:

From the prestressing of the concrete beam and the vibration isolation through to the different pillar patterns between the underground and overground stories, the project involved many technical construction tasks that the engineers would normally have tackled in separate teams with different software solutions.

The solution:

The company used solutions from Allplan and SCIA from Nemetschek for this. The shell or reinforcement plan was created with the help of Allplan Engineering, and modeling and calculations were carried out in SCIA Engineer. ...

Read the full story

Aesthetic shell for regenerative energy

Hydroelectric power station, Kempten

The new run-of-the-river power plant on the Iller river at Kempten impresses the viewer with its dynamic, elegant form. The almost 100 meter long sculptural shell conjures up numerous associations: from whales or waves through to polished boulders. The power plant replaces a building from the 1950s and currently supplies around 4,000 households with a capacity of around 14 gigawatt hours per year.

The challenge:

In a competition, the building client, Allgäuer Überlandwerk (AÜW) Kempten, requested a building design to harmonize with the protected group of buildings opposite, comprising the former Rosenau spinning works and weaving works.

The solution:

The organically shaped shell of the hydroelectric power plant was created with a very high level of detail with
Allplan Engineering and provided the optimum basis for shell and reinforcement plans. ...

Read the full story

Redeveloped efficiently

A2 Freeway, Stansstad-Beckenried, Switzerland

For all those involved in the project, repairs to the 12-kilometer section of the A2 freeway between Stansstad and Beckenried is a particular challenge. Between 2013 and 2017, the section of road, which has been in use for 40 years, will be redeveloped in three construction stages at a cost of around 278 million francs.

The challenge:

The repair work must be carried out within a short space of time, among traffic, and in very tight spaces on site. To meet these demands, the repair work on the Stansstad section to freeway exit Stans Süd, including the preferred measures, has been divided into six phases. It is only necessary to close freeway entrances and exits for a short time during resurfacing work.

The solution:

The project placed high demands on the accuracy of the installation of the new road surface. With Allplan Highway, it was possible to meet these demands very efficiently. ...

Read the full story

Overcoming boundaries

Aare bridge, Olten (SO) Switzerland

Olten has a new landmark: the Aare Bridge, which was given over to traffic in April 2013 as part of the "Olten Region Relief" (Entlastung Region Olten, ERO) project. Thanks to the 3D visualization, the planning association commissioned to manage the project were able to show that the main intersections of the static system could meet all requirements relating to the installation of reinforcements and pre-tensioning measures, despite their minimal dimensions.

The challenge:

The main challenge for reinforcement and pre-tensioning was at the highest point of the structure: The longitudinal beams (which act as a link to the cut-and-cover tunnel), the angled support (which stands on the abutment), and the concrete sail (which braces the bridge's longest support) come together here on both outer sides.

The solution:

The reinforcement and pre-tensioning plans for this level of complexity in the structure could only be tested in the 3D model ...

Read the full story

Island building

Three bridge project in Nijmegen, Netherlands

The Dutch in Nijmegen reveal just how sustainable and pioneering flood protection can be with an impressive project. Just across the border from Germany in the Lower Rhine, Europe's largest flood protection project is under construction. It is called "Ruimte voor de Waal" – literally "more room for the Waal" – and is intended to create more space for the biggest river in the Netherlands, the Waal.

The challenge:

For the engineers in charge at Witteveen + Bos, bridge building on this scale is an enormous challenge, especially as the timetable has been tight from the start. Planning such a major project without errors in such an incredibly short time is only possible – and the Dutch engineers were in full agreement – with hard work and the latest equipment.

The solution:

With Building Information Modeling (BIM) as an efficient planning method, and with Allplan Engineering as the right tool it is extremely beneficial because all the necessary information can be derived directly and coherently. ...

Read the full story

All wrapped up

Elephant house Zurich Zoo, Switzerland

The new Kaeng Krachan Elephant Park at Zurich Zoo is a fine example of the international change taking place in zoo philosophy: More space for elephants, more proximity for visitors. The new home for a family of eight elephants extends over an area of more than 11,000 m². This is approximately six times the size of the old facility and provides the animals with more space, more family life and more room for movement.

The challenge:

The project was a daring experiment because a roof structure like this, with spans of over 85 meters, had never been built before.

The solution:

For many years, Walt + Galmarini has consistently relied on the BIM solution Allplan Engineering for realizing challenging designs with a high degree of quality. Once the digital building model has been populated with the design data, the engineers can derive all the relevant sections, views and perspectives. ...

Read the full story

Nice and slender over the valley

Railway bridge Grubental, traffic project German unity 8.1, Germany

The section of the new line Ebensfeld-Erfurt was planned by the engineering office schlaich bergermann partner and was carried out by the Goldisthal Railway Bridge consortium (Bickhardt Bau AG and Ed. Züblin AG). Situated about five kilometers southwest of Goldisthal in the Thuringian Forest, the 215-meter long structure spans the Grubental Valley at a maximum height of 35 meters and connects the Goldberg Tunnel with the Dunkeltal Bridge.

The challenge:

That's how easy and elegant the Grubental Bridge is, how sophisticated its design is. After all, it was necessary to bridge a narrow valley bordered by steep slopes at an angle of about 50 degrees.

The solution:

Thanks to Allplan Engineering, it was possible to record the difficult terrain situation in a digital terrain model (DTM) in no time. For this purpose, the measurement data provided by the client was ...


Read the full story

Built from the outside in

Airbus Production Hall, Stade, Germany

The various parts of the aircraft are being prefabricated in different locations across Europe to then be assembled in the delivery center in Toulouse, France. In Stade, SHI Planungsgesellschaft mbH (SHI) the Oldenburg-based urban planning, structural and civil engineering company built a modern production hall for a single aircraft component – a 17 meter long, 4 meter wide fuselage shell. The company used the CAD platform Allplan, installed on 25 workstations, to design the hall.

The challenge:

In addition to the sustainability requirements, the design company also had to overcome a number of logistical hurdles during construction of the hall. For example, a crane and a shuttle system had to be fitted in the hall in order to handle large components.

The solution:

For professional implementation of their designs, the SHI team relied throughout on object-oriented work in 3D. “From the outset, Allplan provides us with a transparent design system capable of supporting us through even the most complex tasks. It is not without good reason that we have been using this software for 15 years,“ explains Mr. Wilken. The designers create a three-dimensional model right at the start of the design process. 2D is only used for ...


Read the full story

Art under a straw hat

Centre Pompidou-Metz, Metz, France

A building which houses modern and contemporary art must, itself also, satisfy certain artistic demands. And this is certainly the case at the Pompidou Art Center in Metz: The architects were inspired by the straw hats of japanese rice farmers. This new home for art represents a milestone in the field of architecture and faced structural engineers with a number of challenges. They were solved with Allplan Engineering.

The challenge:

The groundbreaking nature of the building, which was inspired by the image of a rice farmer‘s straw hat, made the structural design a particular challenge: Firstly, the three materials – metal, wood and concrete had to be combined and their static interdependently taken into account. And secondly, the architectural design was very complex due to the optically individual, yet statically overlapping interwoven elements.

The solution:

Two dimensional planning was not sufficient for the challenges of this project, as the complexity of the intersections and the connection points, as well as the high degree of reinforcement required, made 3D tools vital for the reinforcement planning. The interactive functionality of Allplan Engineering provided support in this respect to the CHP planners: depending on requirements, the CAD designers could work with floor plans, isometrics, views and sections in order to create the spatial model. Changes to the reinforcing body were then automatically transferred by the system to all plans and lists. ...


Read the full story

Sweet treats – classically packed

Harrer Chocolate Factory, Sopron, Hungary

One excellent example of a timelessly elegant building that deserves the description “work of art“ is the Harrer chocolate factory located in Sopron, Hungary - specifically a three-story chocolate factory with office and shop.

The challenge:

There were many technical obstacles to overcome, particularly during shell planning. As the construction site previously contained the clay pit of a brickyard, the engineers were required to develop a sophisticated foundation. A five to seven meter thick, non-tight filling layer meant a pile foundation was necessary for the project.

The solution:

To meet the building client’s requirements regarding a short construction period, the experts decided to use a fast production-enabled construction method using cavity wall elements, hollow-core planks and tensioned slab floors ...


Read the full story

Setting the tone with ALLPLAN

Helsinki Music Centre, Helsinki, Finland

Finland, a country which has given the world many famous musicians and composers, is known as the land of music. However, the Finlandia Hall in Helsinki, designed by Alvar Aalto in the 1970‘s, exhibits some serious acoustic drawbacks. This situation should soon be remedied. The Helsinki Music Centre – a new concert hall with sophisticated acoustics – has now opened in the Finnish capital.

The challenge:

When the Vahanen Engineering firm, located in Helsinki, took on the contract for the Helsinki Music Centre, the client had only one condition: project realization should be achieved on the basis of building information modeling. This would ensure that the building met requirements with regard to its design, its function, the costs and deadlines.

The solution:

Vahanen has been utilizing Allplan for the last five years. The engineering company now has seven Allplan Architecture licenses and two Allplan Engineering licenses which were used for the building design, as well as general arrangement and reinforcement design for the Music Centre contract. The Music Centre was designed in 3D. This proved to be an ideal method for designing the building without errors, despite its complexity. The 3D design allowed the engineers to ...


Read the full story

Free froms give firm support

Musiktheater Graz, Austria

The Austrian Federal Real Estate Company (BIG or Bundesimmobiliengesellschaft in German) commissioned the construction of a building for music and musical theatre (or Mumuth for short) for the Graz University of Music and Performing Arts. Planning activities for the building began in 2005. “The planning phase presented us with a few problems. The Mumuth proved to be extremely complex in many respects, including the supporting structure system, the building equipment, the building physics and the facade.

The challenge:

One particular challenge during planning was posed by the ‘Twist,‘ a freely defined spiral element which is the central component of the supporting structure in the foyer. This steel and concrete composite structure begins on the ground floor and spirals upwards through the first and second floors before merging with the ceiling above the second floor.

The solution:

Because the entire geometry consists of free forms, also known as non-uniform rational B-splines (NURBS), it was not possible to simply replicate the Twist in a 3D model without further ado. Instead, it had to be imported into the spatial building model via a less direct route. “We got round this difficult situation by diverting the Terrain module from its intended purpose and using it to ...


Read the full story

Where art and finance merge

Consulting center of Rabobank in Roermond, Netherlands

The inspiration for this building, designed by architecture firm Engelman Architecten in Roermond, was a work by American sculptor Isamu Noguchi. The work of art evokes a snake whose outstretched neck and head reach high into the sky. The architects turned this idea into a two-story building at the end of which a seven-floor tower boldly extends diagonally

The challenge:

In addition to the fact that the sculptural form required an extremely innovative approach for a correct calculation of the main load-bearing structure, another major challenge was ensuring the dimensional accuracy of the precast parts and assembly drawings.

The solution:

To solve these two problems effectively, the designers decided to work in a virtual 3D environment. The entire structure was transferred to Scia Engineer, a modern calculation software that uses the finite element method (FEM). The engineers then subjected ...


Read the full story

BIM for maximum security

Orchidea Tower, Bucharest, Romania

For engineers to retain an overview in a project the size of Orchidea Tower in Bucharest, with 19 stories above ground and 3 below, working with 3D models is practically a must.

The challenge:

Planning was made more problematic by the difficult structural conditions: on the one hand because of the poor quality of the ground close to the river, but above all because of the risk of earthquakes, which had to be taken into consideration in the calculations.

The solution:

From the very beginning, this complex structure was modeled by Inginerie Structurala with Allplan in 3D, using special templates from Scia Engineer designed for steel and concrete construction. No problems were encountered in ...


Read the full story